Our Landmark 489KW Bakula Solar Plant

Project Information
Clients:
Bakula Industries
Capacity:
389 KW (Kilo Watt)
Location:
Mandvi, Surat
Date:
03/12/2025
Ready to Switch to Solar?
Take the first step towards a greener tomorrow. Contact us today for a free consultation and discover how Madhav can transform your energy needs!
Bakula Industries solar project
The Bakula solar plant is a key example of Madhav Solar’s ability to deliver high-performance solar solutions for the industrial manufacturing sector. We are proud to have partnered with Bakula Industries to help them significantly reduce their energy costs and enhance their sustainability.
The execution of the Bakula Solar Plant was completed in a swift 3-month window (January 8 to April 9, 2025). Our team mobilized resources quickly to Tadkeshwar Village, ensuring seamless installation and grid synchronization without delaying the client’s operations. This rapid deployment confirms that the Bakula Solar Plant is more than just an energy source; it is a high-return financial asset. By generating their own power, the client has insulated their business from grid volatility, making the Bakula Solar Plant a benchmark for industrial sustainability in Mandvi.
Client's Goal
Located near a major coal mining zone, the client aimed to set a precedent for green energy adoption. Their primary goal for the Bakula Solar Plant was to drastically reduce high industrial electricity tariffs while showcasing environmental responsibility.
- Reduce high industrial electricity overheads
- Shift energy usage from grid/coal to solar
- Execute project rapidly (Jan-April timeline)
- Achieve quick ROI on 389 KW investment
Results of Bakula Solar Plant
This 389 KW installation is a major asset for the facility. Generating approximately 5.8 Lakh units of electricity annually, it significantly lowers operational costs. This transition aligns with national green energy goals and proves the financial power of our Bakula Solar Project execution.